GRAPEVINE CONSTRUCTION REVIEW
Project Team:
John Wrinkle - Sr. Project Manager
Ben Morrow - Project Manager
Adam Brown - Project Administrator
Kristen Buckalew - Project Administrator
Shawn Gibson - Superintendent
Sam Hanson - Superintendent
Steve Lawhon - Safety Supervisor
Michael Bridges - Field Engineer
Lucinda Drake - Administrative Assistant
MILESTONES
Demolition of the Old Central Utility Plant reached substantial completion June 25, 2009
Grapevine 2nd Floor Labor & Delivery Corridor reached substantial completion June 24, 2009
Grapevine Concrete Repair S & E Parking Lot reached substantial completion June 23, 2009.
SUCCESSES
Baylor Regional Medical Center at Grapevine
Central Utility Plant has been selected to receive a Merit Award in the 2009 Summit Award competition. Thanks for everyone for their contributions in making this another success for the MEDCO and Baylor family. Scott Peek, COO of Baylor Regional Medical Center at Grapevine, had this to say about the recent completion of the concrete repair at the S & E Parking Lot. "The whole team at Grapevine has done outstanding work and I'm sure will continue to do outstanding work that will enhance our ability to serve more patients. We appreciate what you do!!"
PEOPLE
Our goal is to ensure every member of our team goes home safely.
Our families depend on it!

QUALITY
Our standard of quality will limit rework on a daily basis and we will strive to attain a zero punch list at the completion of the projects.

SERVICE
Our goal is to provide 2% savings back to Baylor

FINANCE
Our goal is on time delivery of construction services.

BRMC at Grapevine Interventional Radiology Renovation
In continuing their tradition in providing exemplary health care to the community, Baylor Regional Medical Center at Grapevine has renovated their Interventional Radiology Room making this the fourth Ambient Experience Suite in the nation. This room will offer the patient with a unique like home setting with state of the art equipment that provides multiple sceneries accompanied by the ambient skylight (inset) in order to enhance the patient's comfort and experience during scheduled radiological procedures.
Grapevine Carter Building 6th Floor Finish Out
The 6th Floor finish-out is currently on schedule with all trades and without lost time accidents. Multiple patient rooms have had flooring, wall tile, bathroom accessories, paint, wall protection and headwalls completely installed. Also shown (below) is a prepared nurse station ready for flooring installation scheduled for later this week.
Baylor Regional Medical Center at Grapevine - Emergency Department Parking Garage
The garage precast is nearing completion. MEDCO was behind schedule by approximately 6 weeks due to late approval of the thin brick selections which delayed production. Coreslab Structures and CN Construction were called on by MEDCO to assist in completing the work by the original agreed due date. Through the close coordination of loading cast items when needed and CN Construction working extended hours, working through spring rains, near 100 degree Texas summer heat and Saturdays, the project is now safely on schedule. Currently the parking garage is on schedule and slated for owner occupancy November 19, 2009. Coreslab, Inc. and CN Construction have been instrumental in making this garage project on time and successful.